SUCCESSFUL BID PROTEST, PUBLIC WORK OF IMPROVEMENT CONTRACT

The firm’s client was the second-low bidder on a public works contract for the City of Pomona.  However, the low bidder had not duly complied with the bid requirements.  Specifically, the low bidder had submitted an unbalanced bid with a mathematical error.  The firm  protested that the low bidder’s bid error was a non-material defect which rendered the bid non-responsive.  The City agreed, rejecting the low bid and awarding the project to the firm’s client.

Counsel: Daniel P. Scholz and Madeline L. Gilmore 