Prime contractor on a $12.8 million four school modernization project suffered delay, disruption, and inefficiency damages as a result of unclear plans and specifications, and late completion of predecessor activities by other contractors to the District. The firm prepared the claim and filed suit to collect the damages. Following over a year of litigation and cordial meetings with the District, its counsel, and its experts to explain the claim, the case was mediated to a settlement with the firm’s client being paid $1.2 million for delay and disruption damages, and receiving a thank you letter from the District for building a quality construction project.
Orange County Superior Court Case No. 07CC05300
Counsel: P. Randolph Finch Jr.