Immediately after award on a hard-bid sewer project, the firm’s general contractor client discovered defects in the plans requiring a significant change order. The general contractor requested the change order prior to executing the contract, which the County refused. As a result of the firm’s efforts, the County released the general contractor from the contract without any consequences to its bid bond.
Counsel: Louis J. Blum and Kelly A. Floyd